2022
Upper Valais region, Switzerland
The Riedberg Tunnel is a significant structure on the A9 motorway in the Upper Valais region. The geological conditions in the section near Gampel-Steg, next to the main road heading towards Goppenstein-Kandersteg, pose a particular challenge as the mountain slope is sliding. Investigations revealed that over the past 60 years, it has moved downward at an average rate of around 1 cm per year.
Project Description
As a result of the sliding, construction had to be halted in August 2005 due to slope movement and profile deformations. This occurred at just one year after the start of excavation work for the two 500-meter-long road tunnels, when there was only 133 m of excavation in the north tunnel and 192 m in the south tunnel.
A task force immediately implemented various measures in the following months, such as drainage drilling to minimize water pressure and reduce slope creep. This was carried out in 2006. In 2007, radial jetting with cement injections and toe fillings were implemented. Subsequently, work was stopped to monitor slope movement and to develop a new detailed project.
The aim was to design the tunnel in such a way as to minimize the effects of slope movements and maximize the service life. As a result, the monitoring system was expanded, and since 2012, constructive measures have been implemented. These include stiffening elements in the portal areas, reinforced excavation profiles, ductile design of the inner shell, and 35 cm reserve for any adjustments to the alignment in the standard cross-section.
In spring 2017, excavation work resumed with elaborate reinforcement using steel beams and reinforced in-situ concrete rings. The profile in the already excavated section was widened accordingly. In spring and summer 2022, drainage angles for the lateral drainage system were installed. Shortly thereafter, the drainage layer and waterproofing system started using the innovative fully bonded system SikaProof®-200.
Project Requirements
The demanding geology surrounding the Riedberg Tunnel posed major challenges for planners, engineers, and contractors. A special waterproofing system was needed to ensure full watertightness also with the expected massive movements. The system had to be redundant, maintainable, and reparable.
Here is an overview of the project requirements:
- Protective layer to compensate for unevenness of up to 30 mm in the area of the steel arches.
- Waterproofing: Wrinkle-free installation and good bonding with the concrete inner lining.
- Waterproofing: Even in case of punctured membrane, the waterproofing is resistant to water migration. Tested at 7 bars.
- Special block joint design to accommodate high deformation.
- Concrete inner shell: Self-compacted concrete (SCC) filled up to the roof gap injections are still possible.
- Inspection of the membrane bonding to the concrete with video cameras.
Special Features of this Project
Due to the challenging geology with a sliding slope, a special concept of permanent bearing excavation support was developed. The rock support concrete was acerated on site when placed in situ. The inner lining was poured with self-compacting concrete (SCC).
10 cm wide block joints capable of accommodating larger movements were engineered. The SikaProof®-200 fully bonded waterproofing allows independently sealed blocks without the risk of water migration between the membrane and concrete vault.
Sika Solutions
To protect the tunnel structure from water ingress, SikaBau AG, as the applicator, used the SikaProof®-200 system solution as an “umbrella” waterproofing. The waterproofing FPO sheet, fully bonded to the fresh concrete, was installed on an approximately 28,000 m2 area in the two Riedberg tunnel tubes (with lengths of 536.90 m and 565.30 m) and in the cross-passages.
Also applied were heavy protective geotextiles such as SK Protect and Sikaplan® WT Protection Sheet, which met the requirements of SIA 272 for buildings below ground. For the production of shotcrete and special concrete such as Sikacrete®-16 SCC, various products from the Sika range were used, including: Sika ViscoCrete® SC-403, Sika® Sigunit® L-53 AFS, Sika ViscoCrete®-4027, SikaRapid® C-100, and Sika® Stabilizer-4 R. Enkadrain 20 mm was used as drainage material.
Products Used
Sikaplan® WT Disc
SikaProof®-200
Sikaplan® WT Protection Sheet-20 H, 50 cm strips
Sikaplan® WP Drainage Angle
SikaProof® Fix Tape-50
SikaProof® Patch-200 B
Sika Boom®-131 Multiposition
Concrete admixtures:
Sika ViscoCrete® SC-403
Sika® Sigunit® L-53 AFS
Sikacrete®-16 SCC
SikaPump® Start-1
Sika® Cosmetic
Sika ViscoCrete®-4027
SikaRapid® C-100
Sika® Stabilizer-4 R
Project Participants
Customer
Canton of Valais, Department of National Roads
Contractor
ARGE = JV Tunnel Riedberg Frutiger AG, Prader Losinger AG, Interalp Bau AG
Engineer
Amberg Engineering AG, AFRY + CSD Ingenieurs AG, Site suppervision
Applicator
SikaBau AG, Visp